Submitting and managing an eSTAR - Portal upload, holds, requests and the planted-error case

FDA eSTAR program page, CDRH Portal, 21 CFR 807.87 and 807.100, ISO 13485:2016 clauses 4.2.5, 5.5.1 and 7.2.3

What you will learn

Key takeaways

Free practice question

FDA places Halden's 510(k) on hold. The notice goes to the regulatory lead's personal inbox while she is on leave for six weeks. Nobody else knows the notice exists.

Which control would have prevented the loss of time?

A shared FDA correspondence mailbox with two named monitors and a register of deadlines.

Correct. ISO 13485 clause 7.2.3 expects documented arrangements for communication with authorities, and this removes the single point of failure.

Asking FDA to send notices only on weekdays.

Not quite. FDA does not tailor notice days to the applicant, and weekdays do not solve the absence problem in clause 7.2.3 terms.

Extending the 180 day period by internal policy.

Not quite. The hold period is set by FDA under the program page and an internal policy cannot extend it. Reference: FDA eSTAR program page, section on technical screening and submission.

Printing all notices for the annual management review.

Not quite. Annual review is too late for a 180 day deadline, so it does not meet the arrangement clause 7.2.3 implies.

Key terms

Official sources

Go further

The full lesson has narrated slides, more scenario questions with explained answers and a simulation.

Open the AcademyWatch on YouTube

Illustrative example. Educational only, not legal advice.