Halden batch record BR-4410 rev B for titanium bone screws lists: quantity manufactured 600, quantity approved for distribution blank, release initials with no date. The material line reads "titanium bar, supplier A".

What is the most serious gap in this record?

The record does not show the approved quantity or the material lot, so traceability and release cannot be shown.

Correct. Clause 7.5.1 requires quantity approved and traceability to the extent of clause 7.5.9, and neither is recorded here.

The quantity manufactured is too high for a single batch.

Not quite. Clause 7.5.1 sets no batch size limit, so quantity manufactured is not the gap here.

The supplier name is written in the wrong field.

Not quite. Field placement is trivial; the missing material lot is the real traceability gap under clause 7.5.9.

The record is a revision B and should be revision A.

Not quite. Revision letters follow document control under clause 4.2.4 and do not affect the traceability gap.

Key terms

Official sources

Go further

The full lesson has narrated slides, more scenario questions with explained answers and a simulation.

Open the AcademyWatch on YouTube

Illustrative example. Educational only, not legal advice.