ISO 13485 · Medium · 13 min lesson

Design and development planning, inputs and outputs - clauses 7.3.2 to 7.3.4

ISO 13485:2016 clauses 7.3.1 to 7.3.4, with EU MDR Article 10(9) and Annexes I and II and the US QMSR as context

What you will learn

Key takeaways

Free practice question

Norvane starts the Halo project with a one-page schedule. Reviews will happen when engineering feels ready, and nobody has written down who may approve a drawing. Two engineers later disagree about who owns the battery design.

What does clause 7.3.2 require here?

Plan stages, reviews, responsibilities and authorities, and keep the plan current.

Correct. Clause 7.3.2 lists stages, reviews, responsibilities and authorities as the minimum content of a design plan.

Nothing until a notified body asks for it.

Not quite. Clause 7.3.2 applies to every project from the start and is not triggered by an external request.

Only a launch date and a budget.

Not quite. Dates and budgets are management information, but clause 7.3.2 asks for control content such as reviews and authorities.

A plan written after the design is finished.

Not quite. Clause 7.3.2 requires planning and control during design, and the plan is updated as the design progresses.

Key terms

Official sources

Go further

The full lesson has narrated slides, more scenario questions with explained answers and a simulation.

Open the AcademyWatch on YouTube

Illustrative example. Educational only, not legal advice.