Smart QA Academy  All lessons

MDSAP · Expert · 15 min lesson

Capstone A - mock MDSAP audit: planning, opening meeting, Management and Measurement chapters

MDSAP AU P0002 Audit Approach (audit sequence, chapters 1 and 3), AU P0008 audit time determination (sections 3, 5.2 and 5.3), ISO/IEC 17021-1 clause 9.4, ISO 13485:2016 clauses 4.1, 5.5, 5.6 and 8.2 to 8.5

What you will learn

Key takeaways

Free practice question

Meridian has a main site and a packaging site. The draft time calculation counts only the main site, because the packaging site is small and the processes are the same.

What does AU P0008 require?

Calculate each site separately and add the times; sampling of manufacturing sites is not permitted.

Not quite. AU P0008 section 5.3.5 states that each site is calculated separately and then totalled.

Sample one site and extend the result to the other.

Correct. AU P0008 section 5.3.5 does not permit sampling of design and manufacturing sites.

Ignore small sites in the calculation.

Not quite. The MDSAP procedure AU P0008 contains no size exemption for sites that carry in scope activities.

Calculate time for the main site and add ten percent.

Not quite. The MDSAP procedure AU P0008 uses no flat ten percent; it adds per site according to applicable tasks.

Key terms

Official sources

Go further

The full lesson has narrated slides, more scenario questions with explained answers and a simulation.

Open the AcademyWatch on YouTube

Illustrative example. Educational only, not legal advice.